Skip to main content

Emerald Associates News

P6-Scrubber v8 - New Release

P6-Scrubber v8 - New Release

In version 8.0, we have introduced quality assurance checks, data analysis and auto-scrubbing. Choose from pre-defined validations and create your own to match your company's needs with configurable warn/fail checks. Peruse sleek and responsive reports to see any potential issues in your projects or activities, all bundled together with regular scrubbing capabilities. Dig into schedule details with our project statistics dashboards.

Read more

CAPPS - v14 Release

CAPPS - v14 Release

Introducing CAPPS Version 14.0.

This new version introduces crosstab views, a Gantt chart tab, and Project Data Dashboards. Crosstab views are perfect for project managers, offering quick and easy activity and step progression that can even be done from your phone or mobile device. The Gantt chart allows for a complete view of your activities along a timeline, right from inside CAPPS. Finally, check out our new project data dashboards, built specifically for project managers.

Read more

Upcoming Free Webinars

Upcoming Free Webinars

Upcoming Webinars - Register Now to Join!
  • P6-Scrubber v8 New Release - March 10, 7-8pm MDT
  • P6-Scrubber v8 New Release - March 11, 9-10am Philippine Standard Time
  • BI-GanttView - March 18, 10-11am MDT
  • CAPPS v14 New Release - March 26, 10-11am MDT
  • OPC-Integrator - April 1, 10-11am MDT

Read more

Upcoming Online Training

Upcoming Online Training

Join one of our upcoming, live online training courses for Primavera P6, OPC or Safran Risk.
  • Introduction to OPC - Jan 21-22
  • Primavera P6 Basic - Jan 26-30
  • Primavera P6 Advanced - Feb 9-11
  • Administration in OPC - Feb 18-19

Read more

CAPPS - v13 Release

CAPPS - v13 Release

Introducing CAPPS Version 13.0

Version 13 of CAPPS comes with a completely redesigned and easier to use UI, sophisticated team and user management, better filter and layout management, improved business rule processing in the grid, performance improvements, and more.

Read more

P6-Scrubber v7 - New Release

P6-Scrubber v7 - New Release

In version 7, we added support for scrubbing role codes, revamped the simple scrub dialog (and added new simple scrub areas), and added the ability to apply a dynamic prefix to both IDs and hierarchies in the simple scrub area.

Read more

P6-Loader v15 - New Release

P6-Loader v15 - New Release

In this release of P6-Loader v15, Emerald has added additional UDF merging options for better control. Layouts and filter controls have been greatly expanded, with a layout usage sheet and loader sheet to deal with user layouts. Resources can now be remapped when copying layouts.

Read more

CAPPS - v12 Release

CAPPS - v12 Release

Introducing CAPPS Version 12.0

Version 12 of CAPPS comes with a variety of new features and improvements, including greater grid functionality and adaptability, better clarity, and the addition of a baseline development tab.

Read more

Unifier v24 - New Release

Unifier v24 - New Release

The new Unifier v24.12 update adds significant new features and improvements to make the user experience smoother and easier, including changes to integration, documents and attachments, importing data, the mobile application, and many more.

Read more

P6 v24 - New Release

P6 v24 - New Release

With the new release of P6 v24 comes a flood of enhancements and new features that make P6 better and easier to use than ever! From a new, simple way to unlink your activities in P6 Client, to a whole new view for timesheets in Team Member, take a look at a few of our favorite new additions.

Read more

P6-Loader v14 - New Release

P6-Loader v14 - New Release

Better resource assignment and unique loading options, record action column, and backup of layouts

Read more

P6-Loader v13 - New Release

P6-Loader v13 - New Release

Easier Hierarchies and Fragnet Templating

Read more

P6-QA v8 - New Release

P6-QA v8 - New Release

Your P6-QA metrics are now available in Power BI reports. You can also create custom reports via our P6-Reporter tool in your corporate dashboards. These reports include time based metrics to help you see where in your project these quality issues exist.

Read more

P6-Calculator v7 - New Release

P6-Calculator v7 - New Release

Easily Manage Key Resources and Mandatory Activities in P6!

Read more

Safran Risk v22.2.0 - New Release

Safran Risk v22.2.0 - New Release

Safran Risk has released v22.2.0. Read about all the exciting new features.

Read more

P6-Auditor v5 - New Release

P6-Auditor v5 - New Release

Our latest version of P6-Auditor has a new look and feel making auditing definitions easier and faster to build.

Read more

Safran Risk v22.1.0 - New Release

Safran Risk v22.1.0 - New Release

Safran Risk has released v22.1.0. Read about all the exciting new features.

Read more

P6-Scrubber v6 - New Release

P6-Scrubber v6 - New Release

In version 6, we added notebook type scrubbing and also made improvements to the P6-Scrubber user interface, reports and functionality in general.

Read more

P6-Calculator v6.4 - New Release

P6-Calculator v6.4 - New Release

Easily Manage Key Resources and Mandatory Activities in P6!

Read more

P6-Scrubber v5 - New Release

P6-Scrubber v5 - New Release

Work online or offline to define and scrub your XER files and now, in the new release, XML files. Version 5 makes scrubbing files even easier for schedulers.

Read more

Oracle Primavera P6 20.12.9.0 Released

IMPORTANT UPDATE: The major patch 20.12.9.0 for P6 EPPM is now available. The following list of issues have been fixed for Primavera. To see the other released patches and updates for P6 EPPM v20.12, please visit My Oracle Support.

WEB

33330802 SCORECARD PORTFOLIO VIEW PROJECT NAME HYPERLINKS DO NOT OPEN THE PROJECT BEFORE REDIRECTING TO THE ACTIVITIES PAGE

33319506 FP UPDATE USERS FROM LDAP WITH SELECT ALL USERS - RETURNS NO RESULT

33290833 FP - ERROR: ORA-01795: MAXIMUM NUMBER OF EXPRESSIONS IN A LIST IS 1000 WHEN COPY/PASTE PROJECTS

33277306 P6 WEB APPROVALS TAB TAKES MINUTES TO LOAD

33251166 SORT BY ACTIVITY CODE COLUMN NOT WORKING

33251021 SEARCH FOR ACTIVITY CODE VALUES NOT WORKING IN ACTIVITIES VIEW

33225658 STACKED HISTOGRAM IN RESOURCE ANALYSIS IS NOT SORTING ALPHABETICALLY

33210278 TYPE AHEAD SEARCH IN PROJECT CODE FIELD IN GRID VIEW OF EPS DOES NOT RECOGNIZE CHILD PROJECT CODE VALUES

33197195 FP DURATION DOES NOT CHANGE WHEN DRAGGING ACTIVITY START ON GANTT CHART

33180166 HIERARCHICAL QUERIES CAUSE PERFORMANCE ISSUE WHILE LOADING EPS PAGE WHEN GROUPING INTERVAL IS ONE

33270003 FP - WHEN LOADING ACTIVITES USING P6 API ALL TASKRSRC FOR THE PROJECTS ARE LOADED DURING EACH BATCH

33273500 FP PRIMAVERA WEB SERVICES SYNCHRONIZATION ERROR

33294152 BP- INVALID OBJECT LISTED FOR 20.12.5 NEW INSTALL OR UPGRADE IN 12.1.0.2 ORACLE DB

33173548 20 BP - P6 (WEB) AND P6 PROFESSIONAL USE DIFFERENT RESOURCE CALENDAR WORKTIME WHEN CALENDAR HAS NULL CALENDAR.CLNDR_DATA BLOB FIELD

33279324 BP-CANNOT DOWNLOAD EXCEL XLSX FROM GLOBAL AND PROJECT SECURITY PROFILE PAGES

Team Member

33279132 [OCI MIGRATION ISSUE] ERRONEOUS EMAIL DETAILS FROM TEAM MEMBER VIEWER EMAIL SENDING FUNCTIONALITY

SRVS

33246025 JAVA.LANG.ARRAYINDEXOUTOFBOUNDSEXCEPTION OR JAVA.LANG.NULLPOINTEREXCEPTION SUMMARIZING PROJECT WHICH USES DIFFERENT FINANCIAL PERIOD CALENDAR THAN PROJECT BASELINE

33214484 ERROR IN PARSING THE DATE SELECTING UPDATE HISTORY ON ACTIVITIES VIEW FOR MULTIPLE USERS AND PROJECTS

32883218 SOME P6 PROJECT NOTEBOOK TOPICS PUBLISHING AS 'SPAN>'

P6PRO

33219586 IMPORT XLSX FAILS FOR SPECIFIC PROJECT

33159081 TIME DEFAULTS TO 00:00 WHEN DISABLING DISPLAY TIME IN USER PREFERENCES

33155553 SCHEDULE LOG LOCATION POINTING TO NETWORK DRIVE CAN DEGRADE OVERALL PERFORMANCE WITH SCHEDULING OPERATION

33067059 FS RELATIONSHIPS ARE CREATED WHEN ATTEMPTING TO CREATE SS, SF OR FF RELATIONSHIPS IN THE GANTT CHART

33244525 XML IMPORT – ADVANCED OPTIONS - MISSING OPTION TO “MOVE TO PROJECT” CALENDARS/CODES UNDER ACTION.

33231679 FP - SUMMARIZE PROJECT FAILED

33220683 IN P6 PROFESSIONAL PAGE SETUP > OPTION TAB WHEN BREAK PAGE EVERY GROUP IS SELECTED BUT DISABLED RESULTS IN PAGE BREAKS AFTER EACH ACTIVITY ROW

33219973 ACTIVITIES ARE NOT IMPORTED WHEN IMPORTING PRIMAVERA XML FILE

33210351 LAYOUT REORGANIZES EVEN WITH DISABLE AUTO-REORGANIZATION ENABLED

33173377 SHOW GRAND TOTALS PREVENTS EMPTY EPS NODES FROM BEING DISPLAYED

33121448 EVENT CODE: AVAA0-0396-F CHANGING THE FILTER ON THE PROJECT VIEW FROM CURRENTLY OPEN TO ALL

33037753 WBS ELEMENTS ARE NOT COPYING WPS & DOCS WITH ACTIVITES BETWEEN PROJECTS WHEN THAT OPTION IS SELECTED

Oracle Primavera P6 20.12.8.0 Released

IMPORTANT UPDATE: The major patch 20.12.8.0 for P6 EPPM is now available. The following list of issues have been fixed for Primavera. To see the other released patches and updates for P6 EPPM v20.12, please visit My Oracle Support.

WEB

33149547 INTERNAL-FP:[SQL SERVER] SELECTING A PARENT CODE VALUE ONLY LOADS RESOURCE DATA FOR IMMEDIATE CHILD CODES VALUES ON THE RESOURCE > ANALYSIS PAGE GROUPED BY RESOURCE CODE

33146020 VIEW SERVICE STATUS IMPORT JOB PROJECTS COLUMN SHOWING IMPORTING EPS NAME RATHER THAN THE IMPORTED PROJECTS NAME.

33141555 RESOURCE ASSIGNMENTS VIEW DOES NOT LOAD

33123131 FP - [SQL SERVER] RESOURCE > ASSIGNMENTS PAGE INCORRECT EXECUTES SECOND TASKRSRC STATEMENT WHEN FIRST STATEMENT MATCHES OR EXCEEDS DATA LIMIT AND VIEW CONTAINS UDF OR CODE

33085632 ERROR INVALID PATH WAS REQUEST WAS RECEIVED WHEN TRYIN TO LOGIN IN P6 WEB

33036441 GLOBAL CALENDARS ARE NOT SORTING PROPERLY IN ENTERPRISE DATA

33164010 FP - P6 RESOURCEASSIGNMENT SERVICE ALWAYS RETURNS PRICEPERUNIT AS NULL VALUE FOR A ROLE

33124852 ERROR: JAVA.LANG.NUMBERFORMATEXCEPTION: NULL WHEN LOADING RELATIONSHIPS USING ACTIVITY CLASS.

32999690 EPS IS UNDER FILTER FOR PORTFOLIOS CAUSES AN ERROR

32671449 FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES

32559858 RESOURCE ANALYSIS PAGE TAKES OVER 1 MINUTE TO LOAD

33066149 CHANGE ERROR RETURNED WHEN SUMMARIZING PROJECT WITH NO CALENDAR ASSIGNED

33167149 IN P6 WEB IF A USER IS ASSIGNED A UIV THAT DOES NOT ALLOW ACTIVITY UDF EDITING THE UIV USER IS STILL ABLE TO EDIT THE UDF ON THE LOWER UDF TAB

33130147 SERVICE STATUS PAGE IN P6 IS UNABLE TO LOAD - GETTING AN ERROR

Team Member

33160145 AFTER UPGRADE TEAM MEMBER IS TAKING THREE MINUTES TO OPEN THE PAGE

CLOUDCONN

32986124 CLOUDCONNECT DOES NOT SYNCHRONIZE DATA

P6PRO

33102367 CURTAINS ATTACHMENT NOT PRINTING OVERLAP IN PDF OR PRINT PREVIEW

32818318 P6 SHOWS NOT RESPONDING FOR 8-12 MINUTES WHEN ASSIGNING BASELINES

33124349 IN P6 PRO DURING XER IMPORT IF A NON-DEFAULT IMPORT TEMPLATE IS SELECTED TO USE IT'S SELECTION IS NOT SAVED OFF.

33105897 IN P6 PROFESSIONAL 'STATUS' VALUE IS MISSING FROM THE GROUP BY PICKLIST AND DOES NOT PRE POPULATE THE 1ST GROUP BY ROW WHEN CHOSEN

33104535 P6 VISUALIZER SCHEDULE COMPARISON IS NOT WORKING

33103928 ERROR: EVENT CODE: RRAGC-0089-9 WHEN LEVELING PROJECT

32779443 CORRUPTED BASELINES CREATED INTERMITTENTLY

32617682 FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES

31704565 UNABLE TO LOCK PROJECT AT REQUESTED ACCESS LEVEL WHEN IMPORTING MSP XML FILE TO UPDATE AN EXISTING PROJECT

33202099 SCHEDULE PROJECT SLOW PERFORMANCE IN 20.12.7

32955489 XML IMPORT FAILS TO IMPORT TO SQL SERVER PPM DATABASE

33028808 WEBSERVICE FILTER LASTPUBLISHEDON

Oracle Primavera P6 19.12.16.0 Released

IMPORTANT UPDATE: The major patch 19.12.16.0 for P6 EPPM is now available. The following list of issues have been fixed for Primavera. To see the other released patches and updates for P6 EPPM v19.12, please visit My Oracle Support.

WEB

33165570 DURATION DOES NOT CHANGE WHEN DRAGGING ACTIVITY START ON GANTT CHART

33140229 EMAIL NOTICE SUBJECT DATES AUTOMATICALLY MOVE BACK ONE DAY FROM TIMESHEETS WHEN REJECTING TIMESHEETS

33139557 19 BP - GLOBAL CALENDARS ARE NOT SORTING PROPERLY IN ENTERPRISE DATA

33106454 ERROR: PRICEPERUNIT: CANNOT MODIFY PRICE/UNIT UNLESS RATE SOURCE IS CUSTOM WHEN RUNNING UPDATE BASELINE

33065158 DASHBOARD PORTFOLIO VIEWS GRAPHICS NOT DISPLAYING IN PRINT

33056988 19FP - IN P6 RESOURCES TAB ASSIGNMENTS PAGE WHEN A DIFFERENT VIEW IS SELECTED THE SAVE VIEW MESSAGE POPS-UP UNEXPECTEDLY

33053260 OAS :REPORT GENERATION ARE GETTING FAILED

33023194 INTERNAL-BP:REG: UPDATE BASELINE FAILS WITH ERROR PRICEPERUNIT: CANNOT MODIFY PRICE/UNIT UNLESS RATE SOURCE IS CUSTOM

32900791 INTERNAL-BP:PRE213- PERIOD ACTUAL UNITS ARE INCORRECTLY CALCULATED FOR A SCENARIO IN PROJ ASSIGNMENTS PAGE

32900419 INTERNAL-BP:PROJECT LEVEL COST DISCREPANCY BETWEEN ANALYTICS AND P6

32877915 19 FP - SQLSERVER: FILTER CRITERIA NOT DISPLAYING PROJECTS WHEN THE NUMBER OF EPS/PROJECTS EXCEEDS MAX SETTING

32671439 FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES

31320456 P6 RESOURCEASSIGNMENT SERVICE ALWAYS RETURNS PRICEPERUNIT AS NULL VALUE FOR A ROLE

SRVS

33003631 BP - PROJECT SUMMARIZATION PERFORMANCE DEGRADATION WITH BASELINE COMPARISION SQL

33003598 BP - PROJECT SUMMARIZATION PERFORMANCE DEGRADATION

P6PRO

33178734 CHOOSING CUSTOM DATE FOR PAGE SETUP TIMESCALE DIRECTS TO YEAR 1899

33102358 CURTAINS ATTACHMENT NOT PRINTING OVERLAP IN PDF OR PRINT PREVIEW

31039542 PRINT FUNCTIONS ARE INTERMITTENTLY GRAYED OUT IN P6 PRO ON WINDOWS 2016

33189530 SEVERE DEGRADED PERFORMANCE SINCE APPLYING 19.12.15 FROM 19.12.13

33124357 IN P6 PRO DURING XER IMPORT IF A NON-DEFAULT IMPORT TEMPLATE IS SELECTED TO USE IT'S SELECTION IS NOT SAVED OFF.

33103888 ERROR: EVENT CODE: RRAGC-0089-9 WHEN LEVELING PROJECT

33102373 IN P6 PROFESSIONAL 'STATUS' VALUE IS MISSING FROM THE GROUP BY PICKLIST AND DOES NOT PRE POPULATE THE 1ST GROUP BY ROW WHEN CHOSEN

33025479 THE SCHEDULER PROCESS REQUIRES ADDITIONAL TIME TO COMPLETE - WHEN VIEW LOG FOR FAILED SCHEDULED SERVICE

33015676 SHOW GRAND TOTALS PREVENTS EMPTY EPS NODES FROM BEING DISPLAYED

33005983 ACTIVITIES ARE NOT IMPORTED WHEN IMPORTING PRIMAVERA XML FILE

32797717 SUMMARIZE PROJECT FAILED

32641730 SELECTING FINISH ON A STARTED ACTIVITY THEN MOVING THE FINISH DATE AHEAD CAUSES THE HH:MM TIME VALUE (16:00) TO REVERT TO MIDNIGHT (00:00)

32617677 FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES

32527622 IN P6 PROFESSIONAL PAGE SETUP > OPTION TAB WHEN BREAK PAGE EVERY GROUP IS SELECTED BUT DISABLED RESULTS IN PAGE BREAKS AFTER EACH ACTIVITY ROW

32824832 ASSIGN GLOBAL ACTIVITY CODES IN P6 PRO TO ACTIVITIES - NOT RESPONDING

33086135 EXPORT PROJECT TO MICROSOFT PROJECT XML IS SLOW

Oracle Primavera P6 20.12.7.0 Released

IMPORTANT UPDATE: The major patch 20.12.7.0 for P6 EPPM is now available. The following list of issues have been fixed for Primavera. To see the other released patches and updates for P6 EPPM v20.12, please visit My Oracle Support.

WEB

33053293 OAS :REPORT GENERATION ARE GETTING FAILED

33041114 THE PROJECT ARBITER FAILS AT 3:00 AM DAILY

33029042 BP-ON DELETING CODES/UDF/STEPS NOT DELETED FOR PUBLISED X TABLES

32988267 MISSING CAPTION IN APPLICATION SETTINGS FOR AUDITING

32982399 CLASSIC VIEW MIGRATION FAILED WITH ERRORS

32963106 DATA GETS PUBLISHED IN TO CHGMEMOX TABLE FOR ALL THE PROJECTS THOUGH ONLY SINGLE PROJECT IS PUBLISHED.

32958239 THE USER LOGIN REPORT SHOWS DIFFERENT VALUES UNDER APP_NAME SINCE UPGRADING TO V20.12.4

32936422 WHEN SWITCHING BETWEEN SECURITY PROFILES THE LOWER PERMISSIONS PANE ALSO CHANGES

32877925 20 FP - SQLSERVER: FILTER CRITERIA NOT DISPLAYING PROJECTS WHEN THE NUMBER OF EPS/PROJECTS EXCEEDS MAX SETTING

32876372 WHEN CREATING A NEW GLOBAL DASHBOARD FILTER,USERS RECEIVE THE ERROR: AN ERROR OCCURRED WHILE PROCESSING YOUR REQUEST.

31721941 VIEW SERVICE STATUS IMPORT JOB PROJECTS COLUMN SHOWING IMPORTING EPS NAME

32973049 P6 WEB SERVICES XML EXPORT FAILS WITH: FIELD FINANCIALPERIODTEMPLATEID HAS NOT BEEN LOADED OR SET.

32983183 ACTUALTHISPERIODCOST SET TO LARGE NEGATIVE VALUE WHEN CREATING NEW RESOURCEASSIGNMENTS

33012838 PRIMAVERA P6 IN AZURE - EXPORT PROJECT TO MICROSOFT PROJECT XML IS SLOW

32894598 VALIDATE.BAT, DATABASELOGIN.BAT & DBSETUP.BAT USING SSL PORT GOT ERROR : SQLRECOVERABLEEXCEPTION: IO ERROR: NO APPROPRIATE PROTOCOL ( PROTOCOL IS DISABLED OR CIPHER SUITES ARE INAPPROPRIATE), AUTHENTICATION LAPSE 0 MS

33001533 NEED TO REMOVE DROP SCRIPT IN GET_TASK_CODE_FOR_COPYWBS MSSQL PROCEDURE

32967352 AFTER EPPM UPGRADE FROM V.18.8 TO 20.12 USERS CANNOT COPY WBS COPY WBS FROM TEMPLATE WHEN PROJECT STATUS IS INACTIVE

32929634 COPY WBS FAILED WHEN COPYING A WBS FROM ANY PROJECT OR PROJECT TEMPLATE

P6PRO

33038664 P6 HANGS FOR MINUTES WHEN REFRESHING AFTER SUMMARIZING A PROJECT

32996852 TOTAL ACTIVITY COUNT IN WBS VIEW NOT UPDATED CORRECTLY

32976471 WHILE SWITCHING FROM THE ACTIVITIES VIEW TO WBS VIEW, THE WBS SELECTED IN WBS VIEW IS NOT UPDATED

32801608 IMPORT XML PROCESS COMPLETED SUCCESSFULLY BUT NO PROJECT AND ERROR IN LOG

31514547 IN VISUALIZER TSLD LAYOUT FINISH DATE FILTERS ARE NOT WORKING AS EXPECTED

33030789 LOADING DATA SUMMARY AFTER MANUAL SUMMARIZATION IS TAKING A LONG TIME

32988936 PLANNED VALUE COST DIFFERS IN THE ACTIVITY USAGE SPREADSHEET AND THE ACTIVITY TABLE

32739773 ??INCORRECTRESULTSIZEEXPECTED1ACTUAL0?? INCORRECT RESULT SIZE: EXPECTED 1, ACTUAL 0 WHEN ATTEMPTING TO SAVE A COPY OF THE CURRENT SCHEDULE AS A NEW BASELINE

30505276 THE DATE ADDED IS TODAY'S DATE AND ADDED BY IS SYMON(BG)

32975530 BP - STORED IMAGES CANNOT LOAD AFTER MIGRATING DATABASE

Oracle Primavera P6 19.12.15.0 Released

IMPORTANT UPDATE: The major patch 19.12.15.0 for P6 EPPM is now available. The following list of issues have been fixed for Primavera. To see the other released patches and updates for P6 EPPM v19.12, please visit My Oracle Support.

WEB

32950357 BP OF BUG 32936422 - WHEN SWITCHING BETWEEN SECURITY PROFILES THE LOWER PERMISSIONS PANE ALSO CHANGES

32949812 BP - ALLOCATION NOT CORRECT IN OPEN REQUEST FOR RESOURCES PORTLET

32918176 19 BP - PRE- PORTFOLIO FILTERS ARE NOT SAVING WHEN A DATE FIELD WITH EQUALS OPERATOR IS APPLIED

32821575 P6 WEB CALENDAR DISPLAYED INCORRECTLY FOR 24X7 CALENDAR.

32809022 19 BP - REVOKING A USER'S TIMESHEET MODULE ACCESS WILL CLEAR OUT 'USES TIMESHEET' AND 'TIMESHEET APPROVAL MANAGER' CAUSING INCORRECT APPLY ACTUALS

32808564 19 BP - NO LOCATION FOUND WHEN ENTERING THE GEO COORDINATES

32786472 19 BP - SETTING TIME TO SHOW AS PERCENTAGE DOES NOT WORK, STILL SHOWING DATA AS SHOW AS UNIT/DURATION

32760625 ASSIGNMENTS PAGE P6/REST/ASSIGNMENTS/GRIDDATA/LOAD PROCESSES/SENDS PROJWBS/CALENDAR DATA FROM COLLECTIVE SESSIONS VERSUS THE VIEW BEING LOADED ON PAGE

32729208 SWITCHING FROM DEUTSCH TO ENGLISH WILL MAKE COLUMN NAMES BE DISPLAYED IN DEUTSCH

32718360 PERFORMANCE ISSUE FILTERING/GROUPING UNDER PROJECTS>EPS AFTER OPENING HUNDREDS OF PROJECTS

32713034 19 BP - FILTER CRITERIA CHANGING UNDER MANAGE PORTFOLIOS

32842012 FP - P6 WEB SERVICES XML IMPORT UPDATE EXISTING ERROR: PHYSICALPERCENTCOMPLETE: ACTIVITY PERCENT COMPLETE IS BASED ON ACTIVITY STEPS AND THEREFORE CANNOT BE MODIFIED

TS

32946259 19 BP - TIMESHEETS NOTES SHOW WRONG TIME - MISSING TIMEZONE IN DATE

SRVS

32969998 STRANGE DATA ROW IS GENERATED IN TABLE RESOURCEASSIGNMENTSPREAD

P6PRO

32873918 TOTAL ACTIVITY COUNT IN WBS VIEW NOT UPDATED CORRECTLY

32809298 GETTING EVENT CODE WHEN WE TRY TO ADD ACTIVITY CODES AT EPS LEVEL WITH SQLSERVER DATABASE

32970123 EXPORTING PROJECT FILE SHOWS INVALID FORMAT.

32916897 EXTERNAL EARLY START DATE IS NOT POPULATING IN P6 V19.

32852444 PLANNED VALUE COST DIFFERS IN THE ACTIVITY USAGE SPREADSHEET AND THE ACTIVITY TABLE

32946074 19FP - BASELINE1 SPREAD DATA FOR P6 WEB SERVICES ACTIVITYSPREAD IS INCORRECT